28 February 2007
Demolition was completed a month and a half ahead of schedule. We have started installation of the courtyard that will be accessed from the basement level giving students a gathering area outside the cafeteria. The courtyard is sunk down from the existing elevation 10 feet and its basin is 50 feet by 55 feet. The courtyard has a set 30 wide steps that leads out to the ground level.
We have also installed a new access road to serve as a temporary road for construction. It will eventually become the bus entrance for the school with a bus turnabout at the end of it for loading and unloading students. As we move along, interior finishes will begin this month on the existing building and in the next few weeks we will break ground on the new addition.