Installing the drilled piers Kilgour's Front Lawn

 

Onsite@Kilgour

May 2007

May was a busy month for us, and we've made some great progress.

  • Progress has been made to about top out the walls up to the bottom of the second floor of the new addition
  • South drive parking lot base course of asphalt has been installed
  • Elevator pit has been completed
  • Started the masonry for the connector section between the new and old buildings
  • Asphalt singles have been installed on the existing building
  • Started the membrane roof on the flat portion of the existing building
  • New sidewalk has been installed at the entry of the existing building
  • Complete plaster patch at the first floor of the existing building
  • All partition walls have been installed and the drywall is being finished for the new rooms in the existing building

Thanks for visiting this site. Please check back at the end of each month to get the latest update on our work at Kilgour. Click here to read past issues of Onsite@Kilgour.