September and October were busy months for us as we continue to make great progress on this project.

  • All cmu have been completed at the new addition.
  • Brick cladding at new addition is halfway completed
  • Starting to install windows at existing building
  • Applying final coat finishes at existing building first floor
  • Laying vct flooring at existing building
  • Doing final touches to the basement to get ready for first coat finishes down there
  • Finished all tile at the existing building in the bathrooms
  • Courtyard has been finished