By stalsadmin on
4/23/2012 9:23 AM
The month of March and April have continued to provide good weather for construction work.
|
By stalsadmin on
2/27/2012 4:25 PM
Since the middle of January, significant progress has been made on the addition as well as phase I of the renovation.
|
By stalsadmin on
1/20/2012 1:21 PM
Since the last update, work on the addition has included the lower level concrete slab and concrete masonry walls.
|
By stalsadmin on
12/19/2011 10:13 AM
Since the last update in mid November, construction activities continue to be centered on demolition activities in the existing building and foundation installation for the building addition.
|
By stalsadmin on
11/30/2011 11:26 AM
Since the start of the project in early September, we have been focusing on three specific areas of work: The new front parking lot, the new addition, and the demolition work required for Phase I of the renovation.
|